Micro-surfacing is scheduled to begin Monday, July 15th, 2024 until Friday July 19th, 2024. Viking Construction will mobilize to the City of Bellmead to laydown over 56,000 sy of micro-surfacing material. We ask that all residents impacted on streets scheduled to please relocate vehicles, trailers, campers, etc. out of the roadway to assist with minimizing any inconveniences during the micro-surfacing process. Viking construction will be going through and delivery door tags to streets scheduled. Please see below the anticipated schedule for next week:
Street Start & Stop
Mon, 07/15
Coral Reef Treasure Island to Paridise Island Dr.
Coral Reef Treasure Island to Katy
Bongard Concord to Bongard Cir.
Bongard Bongard Cir. to Bongard Cir.
Harrison Loop 340 to Penton
Lopez Harrison to Gram
San Jose San Pedro to Camp Ground Rd.
Tue, 07/16
Butterfly Way Pecan to Dead End
Hatcher Ashleman to La Vega
Bronco Circle C to Dead End
Circle C Bronco to Wrangler
Colonial Liberty to Concord
San Jacinto Utah to Meyers Ln.
Victoria Harrison to Bellmead Dr.
Wed, 07/17
Dewey - Pinkney Taylor to I-35 Frontage Rd.
Elling Old Dallas Rd. to Queens
Behrens Circle I-35 to New Dallas
La Vega Bellmead Dr. to Harrison
Maxfield Hatcher to Parrish
Thu, 07/18
Treasure Island Rd Coral Reef Rd to Cove Dr
Paradise Island Rd Coral Reef Rd to Cove Dr
Fri, 07/19
Hogan Ln Bellmead Dr. to Beale St
Hogan Ln Beale St to Shelton St
Montrose Old Dallas Rd. to Railroad
Unscheduled Streets
Treasure Island Rd Coral Reef Rd to Cove Dr
Paradise Island Rd Coral Reef Rd to Cove Dr
Hogan Ln Bellmead Dr. to Beale St
Hogan Ln Beale St to Shelton St