Micro-surfacing is scheduled to begin Monday, July 7th, 2025 until Friday July 25th, 2025. Viking Construction will mobilize to the City of Bellmead to laydown over 71,000 SY of micro-surfacing material. We ask that all residents impacted on streets scheduled to please relocate vehicles, trailers, campers, etc. out of the roadway to assist with minimizing any inconveniences during the micro-surfacing process. Viking construction will be going through and delivery door tags to streets scheduled. Please see below the anticipated schedule for next week:
Street Start/Stop
Mon, 07/07
Flyer St. Fenton St. Limited St.
Calvery St. Katy Ln. End
Tue, 07/08
Walton Dr. N Loop 340 Bank Dr.
Briarwood Ln. I-35 Frontage End
Behrens Cir. New Dallas Hwy Montrose St.
La Clede St. Wheeler St. Parrish St.
Maxfield St. Wheeler St. Parrish St.
Crestline St. Wheeler St. End
Wed, 07/09
Montrose St. Stickland Behrens Cir.
Bank Dr. N Loop 340 N Loop 340
Redbird St. Fisher St. Barlow St.
January St. Latimer St. Hatcher St.
Springhill St Timberline St Blackwell St
Thu, 07/10
Carla St. Katy Ln. End
Tue, 07/15
Harrison St. Fisher St. Kane St.
Wilder St. La Clede St. Ashleman St.
Beale St. Hogan Ln. Maxfield St.
Wed, 07/16
Harrison St. Penton Williams
Michigan St. Hwy 84 Cloverleaf Rd.
Bongard Cir. Bongard Cir. Bongard Cir.
Thu, 07/17
Timberline St. Duggar St. Blackwell St.
San Jacinto St. Utah St. Concord Rd.
Circle C Wrangler Rustler Dr.
Tue, 07/22
Cove Dr. Williams Dr. Paradise Island Rd.
Lopez St. Gram Ln. Williams Rd.
***patches / clean up***